After several months of preliminary work involving the shipping, installing and testing CAT diesel generators, spare parts, fuel systems, and miscellaneous plant equipment, USP&E is preparing to commission the power plant of a large industrial client in Africa the week of June 1st. Carl Daughtery, our power plant superintendent, has a team of 15 non-local and 25 local men and women who are assisting with this project. After many months of working 7 days per week in severe conditions, USP&E is very excited about this commissioning project and the value added by our expertise and creative solutions implemented to get this 50mW power plant completely installed and commissioned in record time. USP&E: Powering Business. Empowering People.